Week 1

  • Site establishment (signage erection, temporary fencing & toilet, skip waste bins)
  • Demolition if any
  • Site clearout, levelling and groundwork including utilities connections (Storm water, sewerage, Gas and Electrical services)

Week 2

  • Excavation
  • Pad footings concrete pouring (Boxspan flooring system) or formwork and concrete slab pouring
  • Termite protection to whole floor area as per Australian standards.

Week 3

  • Steel Wall frames installation and precise calibration
  • Roof Trusses Installation and precise calibration
  • Colour bond fascia and gutters installation
  • Eaves and roof installation
  • Window installation
  • External doors installation

Week 4

  • External façade cladding
  • Lock up point of the project
  • Internal Plumbing rough-in
  • Internal Electrical rough-in

Week 5

  • Walls and ceiling insulation as per eco friendly high performance Australian standards
  • Internal walls plasterboard covering and setting
  • All wet areas to be waterproofed to Australian standards

Week 6

  • Floor and wall tiling of bathroom & laundry
  • Floor finishes as per package and selection
  • Kitchen fit-out

Week 7

  • Plumbing vanities installation in bathroom, laundry and kitchen
  • Internal doors fixing
  • Skirting and architraves fixing
  • Wardrobes fit-out and adjustment
  • Internal & external painting

Week 8

  • Kitchen appliances Installation
  • Hot water unit installation
  • Electrical fit-out and power meter connection
  • Detailed internal and external cleaning
  • Troubleshooting and building inspection as per contract
  • Handover of keys and certification to owner