- 1. Site preparation & foundations
 - 2. Framing & lock-up stage
 - 3. Finishes & decorations
 - 4. Cleanup & commissioning / Handover
 
Week 1
- Site establishment (signage erection, temporary fencing & toilet, skip waste bins)
 - Demolition if any
 - Site clearout, levelling and groundwork including utilities connections (Storm water, sewerage, Gas and Electrical services)
 
Week 2
- Excavation
 - Pad footings concrete pouring (Boxspan flooring system) or formwork and concrete slab pouring
 - Termite protection to whole floor area as per Australian standards.
 
Week 3
- Steel Wall frames installation and precise calibration
 - Roof Trusses Installation and precise calibration
 - Colour bond fascia and gutters installation
 - Eaves and roof installation
 - Window installation
 - External doors installation
 
Week 4
- External façade cladding
 - Lock up point of the project
 - Internal Plumbing rough-in
 - Internal Electrical rough-in
 
Week 5
- Walls and ceiling insulation as per eco friendly high performance Australian standards
 - Internal walls plasterboard covering and setting
 - All wet areas to be waterproofed to Australian standards
 
Week 6
- Floor and wall tiling of bathroom & laundry
 - Floor finishes as per package and selection
 - Kitchen fit-out
 
Week 7
- Plumbing vanities installation in bathroom, laundry and kitchen
 - Internal doors fixing
 - Skirting and architraves fixing
 - Wardrobes fit-out and adjustment
 - Internal & external painting
 
Week 8
- Kitchen appliances Installation
 - Hot water unit installation
 - Electrical fit-out and power meter connection
 - Detailed internal and external cleaning
 - Troubleshooting and building inspection as per contract
 - Handover of keys and certification to owner
 